For a first production run, plan for 8 to 16 weeks from signed agreement to finished goods. This includes raw-material procurement (2 to 4 weeks), formula setup and compatibility testing (1 to 3 weeks), sample approval (1 to 2 weeks), and production plus filling (2 to 4 weeks). Complex formulas, custom packaging, or novel actives can extend timelines. AJ Cosmo Labs push notifications keep you updated at every milestone.